5.2
Phase-Out Plans. Describe the phase-out plan for any equipment identified for removal
(include equipment, spare parts and documentation at all levels of support). Identify by
nomenclature and name all existing equipment that will be removed as part of this
project. This may include utilizing the equipment to augment the supply infrastructure,
availability for foreign military sales, demilitarization and safety hazards. If available,
the EILSP for the phased-out system/equipment shall be updated to reflect phase-out
plans.
5.2.1
Equipment Phase-Out. Identify by nomenclature, name and part number all equipment
that will be phased-out as part of the project.
5.2.2
Phase-Out Schedule. State the phase-out schedule for replaced equipment when new
acquisition occurs.
5.2.3
Disposition of Phased-out Material. State how phased-out equipment will be disposed of,
who will initiate required documentation (including configuration change forms). State if
any hazardous material or precious metal is involved.
SECTION 6.0 - SUPPLY SUPPORT
6.1
Supply Support Concepts. Describe the supply support (commercial, reimbursable, etc.)
for this equipment. The supply support concept must be consistent with the supply
support concept identified in the ILSP for the end-item system. Briefly summarize
proper identification, planning and budgeting of spare parts.
6.2
Supply Requirements. The Project Officer should ensure the following support elements
have been considered, either in the EILSP or other appropriate support documents.
Where applicable, reference the appropriate support document.
Item name (equipment, publication, part)
Item nomenclature, model number or publication number
Who will supply the item
When items will be supplied
Manufacturer Commercial and Government Entity (CAGE) code or name
Item cost
Physical weight for each item and total for stored quantity
Cubic feet for each item and total for stored quantity
Security Requirements (if applicable)
Shelf life (if applicable)
6.2.1. Organizational Level. List parts to be issued and maintained as spares at this level and
reference applicable support documents. Describe the method the unit will use to obtain
replacement parts, assemblies, and equipment. Items should be listed to the Lowest
Repairable Unit (LRU).
6.2.2
Intermediate Level. Identify the unit(s) or facility that will serve as this level of supply
support. State what parts will be issued and maintained at this level and reference
5