Appendix A - Summary A-76 Analysis Tree for ISSA's/Orders to
Other Government Agencies
Is it done by contract or in-house?
________________________|__________________________
|
|
In-house
contract
|
|
|
|
Is there statutory authority
Is existing work
other than Economy Act?
within contract scope?
|
|
_____________|_______________
____________|____________
|
|
|
|
|
|
|
|
Yes
No
Yes
No (2)
|
|
|
|
|
|
Proceed under
Is it covered by
Proceed
that other
an A-76 exemption?
|
authority
____________|____________
|
|
|
|
|
| Is expansion/extension
|
|
needed?
|
|
__________|____________
Yes
No |
|
Can continue and
| No
Yes
expand as long as
|
|
within scope of
|
Is expansion within
exemption
contract scope?
|
_________|______
|
|
|
|
No
Yes
termine most economical/convenient
|
|
______________|_______________
|
Proceed
|
|
|
Yes
No (3) |
|
|
Was cost comparison
______ |______
Conducted? (1)
|
|
_______________________|______________ Compete
Justify
|
| requirement
sole source
Yes
No
|
|
|
_____________________|__________________
Proceed
|
|
|
Conduct new
justify as
contract
cost comparison
core or sole
source
Note 1. Earlier cost comparison not sufficient if exceeds scope of that comparison.
Note 2. Corrective action is required
Note 3. If cannot justify under Earliest feasible contract competition Economy Act, contract. is
preferred action. Sole source may be possible but will get close scrutiny.
A-1