Enclosure (1) to COMDTINST 16000.27
NIMS AND NRP ALIGNMENT CERTIFICATION CHECKLIST
(Local reproduction authorized)
Name of Plan:
Date:
Plan Holder (Unit):
Ref:
(a) National Incident Management System (NIMS), 1 March 2004
(b) National Response Plan (NRP), December 2004
(c) Alignment with the National Incident Management System and National Response Plan,
COMDTINST 16600.27 series
(d) United States Coast Guard National Incident Management System (NIMS) and National
Response Plan (NRP) Implementation Plan, 29 December 2004
1. The following actions have been taken to align this plan with references (a) and (b), consistent with
the guidance provided by reference (c). (Check boxes as appropriate.)
[ ] This plan prescribes the use of the Incident Command System (ICS) as per the National
Incident Management System (NIMS), reference (a).
[ ] This plan meets the requirements of reference (a) or corrections have been made where
practicable to address minor changes necessary for consistency with reference (a).
[ ] This plan meets the requirements of reference (a) or corrections have been made where
practicable to address minor changes necessary for consistency with reference (b).
[ ] Supplemental pages listed as Attachments to this certification have been prepared and
included as attachments to this certification to address NRP alignment issues beyond minor
changes.
[ ] This plan is scheduled for a formal revision to be completed by ______________ (insert
required completion date) in accordance with reference (d).
2. When this plan is executed, it will supplement the overarching core coordinating structures,
processes, and protocols detailed in the NRP. Figure 1 of attachment (a) depicts the NRP
coordinating structures specified by reference (a). This figure is included in this revised plan.
(Name of person responsible for changes)
(Title)
Attachments:
(a) - Structure for NRP Coordination
1