Encl. (4) to COMDTINST 16200.3A
Table 4-A.
Bridge Administration Civil Penalty Ranges
1.
Approved Location and Plans (33 U.S.C. 401, 491 & 495):
a.
Construction or modification
of bridges without Coast
Guard approval (33 CFR 115.50(b)):........0-1,000/day
b.
Deviation from approved
plans without prior Coast
Guard approval (33 CFR 115.50(b)):........0-1,000/day
2.
Bridge Permit Conditions (33 U.S.C. 525(b)):
a.
Deviation from approved
plans for temporary bridge:.........................0-500/day
b.
Failure to display and
maintain clearance gauges:..........................0-450/day
c.
Construction of falsework,
cofferdams, or other
obstructions without prior
Coast Guard approval:...............................0-1,000/day
d.
Timely notice not given of
construction or modification
events affecting navigation:........................0-1,000/day
e.
Channels through the structure
not cleared of construction
obstructions within time limit:.....................0-1,000/day
f.
Failure to remove existing
bridge, which will not be
replaced when no longer used
for transportation purposes,
to specific elevation within
time limit:.........................................0-1,000/day
g.
Failure to remove temporary
bridge to specific elevation
and clear waterway within
time limit:.........................................0-1,000/day
h.
Failure to remove existing,
to be replaced, bridge to
specific elevation and clear
waterway within time limit:.........................0-1,000/day
3