COMDTINST 5200.16
i. No application(s) that require any type of video, including teleconferencing and
streaming, or any type of audio, including voice transmission may be tested or
implemented on the CGDN+ without approval from the SWIII CCB due to bandwidth
considerations and impact on the CGDN+.
j. If evaluation hardware and/or software are loaded onto testbed systems(s), those
testbeds shall not be connected to the CGDN+ without prior approval from TISCOM.
k. All requests for non-standard microcomputer hardware must be evaluated either by a
Program Manager for enterprise AIS or by the responsible LCCB for all other user
requests. Should the Program Manager or LCCB choose to pursue the request for non-
standard equipment, an ECP which includes life cycle costs is required and the package
shall be submitted in accordance with reference (f).
l. Category C applications will be removed by the LCCB if they are in conflict with
Category A and/or Category B applications.
m. TISCOM is charged with maintenance and support of the standard image for SWIII
workstations and internal server architecture. TISCOM may develop and deploy
routines to accommodate vendor service releases and updates, bug fixes, performance
tuning, modifications required by CG instruction, law or other government regulation,
modifications required as a result of other CCB actions as well as updates, patches, and
modifications to system utilities, approved accessories and user tools without the
requirement to submit an ECP.
7.
PROCESSES.
a. All requests for changes to the SWIII Baseline will first be reviewed by the responsible
LCCB. If the change is to be implemented only on a local basis (Category C), the
LCCB will evaluate the request presented in an LCCB defined format. TheLCCB may
approve the request if it is found to be technically feasible, supportable, meets a local
business need and funding is identified. The LCCB shall notify TISCOM Information
Systems Directorate (TISCOMisd) of the local change. TISCOMisd will maintain a
SWIII CM Knowledge Base containing information on LCCB approved local changes.
This information will be accessible to all SWIII support organizations. The database
and the process of data submission are under development.
b. If the change request covers a MEA or a CG-wide enterprise application and the change
impacts the CG-wide SWIII baseline (Category B), the sponsor shall develop a SWIII
ECP and Standard Lifecycle Cost Sheet (SLCS), enclosures (2) and (3), and submit
them to the SWIII CCB Chairman. The SWIII CCB shall evaluate it as outlined in
paragraph 6.b. above. If approved, TISCOM shall work with the sponsor to ensure that
Certification Testing is completed and the CM Knowledge Base is updated. For CG-
wide enterprise applications developed through the A109 Major Acquisition Process,
and thus approved at
5